|
FRUSTRATION OF CONTRACT & IMPOSSIBILITY OF
PERFORMANCE
Karnika Seth
The doctrine of frustration is of great significance in the
International Trade transactions, as also, are the Force Majeure clauses
since there is a greater element of uncertainty in cross border
transactions as compared to purely domestic transactions as they are
subject to diverse political and economic influences. While the English
Law envisages the doctrine of frustration of contract, the American
Uniform Commercial Code provides for commercial 'impracticability' where
such impracticability affects the basic assumption on which the contract
was made (however in English law the term 'Impossibility' is generally
used). The French system admits "Force Majeure" whereas the German
advances the notion of "Wegfall der Geschftsgrundslage "- collapse of
the basis of the transaction. The principles on which the doctrine of
frustration is based are well settled. However, the application of the
doctrine sometimes involves complicated analysis. Lord Diplock in
Pioneer Shipping Limited Vs. BTP Dioxide Ltd, the NEMA expressed his
view as under:
"Never a pure question on fact but does in the ultimate analysis involve
a conclusion of law as to whether the frustrating event or series of
events has made the performance of the contract a thing radically
different from that which was undertaken by the contract".
Frustration of a contract occurs only where after the conclusion of the
contract a fundamentally different situation has unexpectedly emerged.
The emergence of some new set of circumstances may make the performance
of the contract more difficult, onerous or costly than was envisaged by
the parties when entering into the contract, for example, a sudden, even
abnormal, rise or fall in prices or the failure of a particular source
of supply requiring the seller to obtain supplies from another more
expensive source. However, these events will not normally operate to
frustrate a contract. This position was discussed in the British
Movietonews Ltd. Vs. London & District Cinemas Ltd. However, an
important exception was also recognised by the House of Lords in this
case that "if on the other hand a consideration of the terms of the
contract, in the light of the circumstances existing when it was made,
shows that they never agreed to be bound in a fundamentally different
situation which has now unexpectedly emerged, the contract ceases to
bind at that point not because the Court in its discretion thinks it
just and reasonable to qualify the terms of the contract but because on
its true construction it does not apply in that situation."
* Advocate practising in Supreme Court Of India and High Court Of Delhi
Lord Radcliffe in Davis Contractors Ltd. vs. Fareham UDC, reiterated
these principles as "frustration occurs whenever the law recognizes that
without the default of either party a contractual obligation has become
incapable of being performed because of the circumstances in which
performance is called for would render it a thing radically different
from that which was undertaken by the contract".
These principles were applied in many cases such as Amalgamated Inv and
property Co. V John Walker& Sons , National carriers V Panalpina ,etc
In Brauer & Co. (Great Britain) Ltd. Vs. James Clerk (Brush Materials)
Ltd Denning LJ held that the sellers of the Brazilian Pissava, a woody
fibre used in making of the brush and the like, under a CIF contract
containing the clause "subject to any Brazilian Export Licence" were not
relieved of their obligation to procure a licence due to escalation in
prices by 20% to 30% in excess of prices agreed upon with their buyers.
Denning Ltd., however, stated that if the price was a 100 times high as
much as the contract price that would be a fundamentally different
situation which had unexpectedly emerged and the sellers would not be
bound to pay for the escalated price of the export licence.
Cyber
law - Blogs, News and Articles : The Internet, Cyber World Technology -
India International - Visit
www.cybersmart.in
On the happening of unexpected events which are beyond the control of
the parties such as in case of Government Prohibition of Exportation or
Importation or a strike or other industrial actions, sellers often take
the benefit of the force majeure clauses that may be expressly provided
for in a contract or on the principle of frustration of contract in the
domain of general law. In these cases the contract may at the beginning
of the event in question merely be suspended and later on become
frustrated after lapse of reasonable time when it is evident that the
delay caused by intervening event affects the foundation of the
contract. Certain other examples that would attract the application of
this doctrine have been seen in cases where there is a complete
destruction of subject matter in an agreement to sell specific goods,
illegality in cases of out-break of war i.e. where the legality of
performance of a contract is affected by war.
A contract may also be frustrated because subsequent to its conclusion,
the Government has prohibited its performance for instance by placing an
embargo on the exportation or importation of goods sold in situation
other than wartime which absolutely prevents the seller or buyer from
performing a contract. However, sometime the governmental prohibition
may be only conditional or it may be only temporary. Such Governmental
prohibition operates as a frustrating event only if it is final and
extends till the whole time still available for the performance of the
contract. In a landmark case popularly known as Suezcanal case, the
House of Lords analysed a situation wherein Suezcanal was closed on
November 2nd, 1956 as a result of military operations between Egypt and
Israel and the exporter in east Africa who had sold certain goods for
shipment CIF specifying European destination, on the date of performance
the Suezcanal was closed could not ship the goods via that route. The
House of Lords took the view that it was still possible to ship the
goods to their destination via the Cape of Good Hope and the seller
could have performed the contract although that route was not only
longer but would result in Sellers' incurring considerable expense. The
important question which was decided, in the negative, was whether the
necessity to ship by alternative route constituted a radical difference
in the character of the seller's obligation.
Unlike English law, the United States has abandoned the word
"impossible" and used the term "impracticable". The "impracticability"
of performance of contract includes situations of extra and unreasonable
difficulty, expenses, injury or loss to one of the parties. Examples
include a severe shortage of raw materials or of supplies due to war,
embargo, local crop failure, unforeseen shut down of major sources of
supply or the like peculiar situations. According to UCC Section 2 - 611
a need for increased cost alone does not excuse performance but it is
suggested that a price increase well beyond the normal range would lead
to discharge (Re-statement 2(d) contract 261 Comment (d).
In England, dicta to the effect that a contract may be discharged if its
performance becomes impracticable are occasionally found in some cases
such as Horlock Vs. BEAL , the Furnace Bridge , Andre & cie v Tradax
Export SA .
It is pertinent to note that , by and large the English precedents
illustrate the view that impracticability is not generally sufficient to
frustrate a contract in English Law. In Davis Contractors Ltd. Vs.
Fareham contractors agreed to build 78 houses for a local authority in
eight months for £ 94,000. Because of labour shortages the work took 22
months and cost the contractors £ 115,000. They claimed that the
contract had been frustrated and that they were entitled to extra
remuneration but the House of Lords rejected the claim as the events
which caused the delays were within the ordinary range of commercial
probability and had not brought about a fundamental change of
circumstances.
In Exporttelise V Rocco Giveppe & Figlisoc.coll case, an organ of
Argentine State which was sole buyer of bread wheat extended its
monopoly to include the 1973/74 crop of candal and/or taganrog wheat. No
exceptions were made for existing contracts and the monopoly was
maintained throughout the period of shipment. The Argentine Exporter so
as to to export wheat had to obtain from Juntu at a price higher than
the price at which the Argentine exporters had resold the wheat. The
Court held that this act of the Government did not render every method
of fulfilment of the contract impossible and the sellers could still
have bought the wheat necessary to fulfil their obligations under the
contract.
It is important to note that in Brauer & Co. (Great Britain) case cited
hereinabove, the Justice Singlton held that prima facie the risk of an
increase in the price of goods is upon the seller. The sellers could not
be covered under the force majeure clause merely by showing that they
were required to pay more for the goods than the price at which they had
agreed to sell them, that goes no farther than showing that in the
events which happened they have entered into an unprofitable contract
which provides no answer. It was important to note that the sellers
could have performed the contracts if they had paid the higher minimum
price since there was no physical or legal prevention from doing tjhe
same but only an escalation of prices of export licence to be procured
by the sellers in order to duly perform the contract.
In Wild Handel NV Vs. Tucker and Cross , the sellers invoked the force
majeure clause of the contract of sale of Chinese frozen rabbits. The
sellers contended that the imports of Chinese frozen rabbits were at all
material time much smaller in quantity than the amount called for under
their contract. The Court held that there was no finding from the
arbitrator that they were unable to buy the Chinese frozen rabbit from
some supplier other than the one with whom they have a contract. Justice
Donaldson expressed that unless they could do that they are unable to
show that they were prevented from fulfilling the contract by a cause
beyond their control.
In the light of the above discussion, it follows that there are certain
important factors that require consideration at the time of analysing
whether an unexpected event could be said to cause frustration of
contract or whether the force majeure clause is attracted as per and/or
within the meaning of the terms of the contract. Some of the important
questions that require consideration may be enumerated as under:
1. Does the contract contemplate that if 'X' fails to supply the goods
to the seller, the seller is obligated to procure the specific goods
from any other alternative source( irrespective of the fact whether the
same would be commercially viable or not). Has this intention of the
parties been expressly provided for in the contract, or is it in
contemplation of both parties but not expressly mentioned in the
contract or is it only a one sided contemplation?
2. Does unexpected escalation in freight charges render the price
abnormally excessive or the contract execution impracticable; such that
it would amount to a contract fundamentally different from one
contemplated by the parties?
3. Is there any Government regulation that prohibits the export/
importation of goods? Is it temporary or exists upto the period of
performance of contract. Does it absolutely prevent the seller or the
buyer from performing the contract or make the performance of contract
illegal?
4. Is the payment of unexpected /escalated higher price reasonably
foreseeable by the parties at the time of entering into the contract?
5. Is this supervening unexpected event beyond the control of the
parties?
To conclude, these factors are in fact requisites to attract the
doctrine of frustration of contract and force majeure clause contained
in any contract, in particular, a sale of goods contract .In English Law
whereas the decisions rendered by the Courts could vary on principal
facts of the case, however, the basic principles that attract the
doctrine of frustration and force majeure clauses by and large remain
the same.
Bibliography
1.The Law and Practice of International Trade-Schmitthoff's Export
trade- Sweet & Maxwell 2000 Edn.
2.The law of Contract- Treitel-Sweet & Maxwell- Ninth Edn.
3. Sale of Goods- Benjamin, Sweet & Maxwell-Second Edn
4.Halsbury's Laws of England- Vol 9 (1) Fourth Edn.
5.Chitty on contracts- Specific contracts- Sweet & MAxwellTwenty Eighth
Edn.
6.The Sale of goods Act -Aiyar-UBA Seventh Edn.
Karnika Seth is a practising Advocate in
the Supreme Court of India and the Delhi High Court and is a legal
advisor to both Foreign and Indian Clients in the field of Cyberlaws,
Information Technolgy ,International Trade and Intellectual Property
Rights.
Ms. Seth is a Visiting Lecturer to the Indian Law Institute and the
Amity law School, New Delhi where she teaches specialized courses in
Cyber laws and Intellectual Property Rights. She has been invited as a
Guest speaker to deliver presentations on issues relating to
Internet/cyberlaws by the Indian Council of Arbitration ,Amity Law
School, Delhi, Amity Law School, Chandigarh, Rajasthan Chapter of
Commerce and Industry ,Indian Law Institute and other prominent
Institutions.
Her papers on the subject of Cyberlaws, Arbitration, Contract Laws
,Intellectual property laws have been published in reputed Legal
Journals and newsletters such as the Indian Council of Arbitration
Newsletter, Amity Law Review ,Patent and Trademark Reporter, Lawyers
Update and other legal journals.
You may mail your queries to the author at
Karnika@sethassociates.com.
Copyrighted 2005 Karnika Seth. Permission
to make digital or paper copy of these works for personal or classroom
use is granted without fee provided that the copies are not made or
distributed for profit or commercial advantage .It is permissible to
abstract these works so long as credit is given. To copy in all other
cases,or to republish it or post on a server or to redistribute requires
special permission from Author at
karnika@sethassociates.com
More Cyber Law
Articles and News - www.cybersmart.in
|