Secrets of Successful Project Management !!!
Managing software projects is difficult under the best circumstances.
Unfortunately, many new project managers receive virtually no job
training. Sometimes you must rely on coaching and survival tips from
people who have already done their tour of duty in the project
management trenches. Here are 20 such tips for success, which I’ve
learned from both well-managed and challenged projects. Keep these
suggestions in mind during your next project, recognizing that none of
them is a silver bullet for your project management problems.
Laying the Groundwork
Tip #1: Define project success criteria. At the beginning of the
project, make sure the stakeholders share a common understanding of
how they will determine whether this project is successful. Too often,
meeting a predetermined schedule is the only apparent success factor,
but there are certainly others. Some examples are increasing market
share, reaching a specified sales volume or revenue, achieving
specific customer satisfaction measures, retiring a high-maintenance
legacy system, and achieving a particular transaction processing
volume and correctness.
Tip #2: Identify project drivers, constraints, and degrees of freedom.
Every project needs to balance its functionality, staffing, budget,
schedule, and quality objectives. Define each of these five project
dimensions as either a constraint within which you must operate, a
driver aligned with project success, or a degree of freedom that you
can adjust within some stated bounds to succeed. For more details
about this, see Chapter 2 of my Creating a Software Engineering
Culture (Dorset House, 1996).
Tip #3: Define product release criteria. Early in the project, decide
what criteria will determine whether or not the product is ready for
release. You might base release criteria on the number of
high-priority defects still open, performance measurements, specific
functionality being fully operational, or other indicators that the
project has met its goals. Whatever criteria you choose should be
realistic, measurable, documented, and aligned with what "quality"
means to your customers.
Tip #4: Negotiate commitments. Despite pressure to promise the
impossible, never make a commitment you know you can’t keep. Engage in
good-faith negotiations with customers and managers about what is
realistically achievable. Any data you have from previous projects
will help you make persuasive arguments, although there is no real
defense against unreasonable people.
Planning the Work
Tip #5: Write a plan. Some people believe the time spent writing a
plan could be better spent writing code, but I don’t agree. The hard
part isn’t writing the plan. The hard part is actually doing the
planning—thinking, negotiating, balancing, talking, asking, and
listening. The time you spend analyzing what it will take to solve the
problem will reduce the number of surprises you have to cope with
later in the project.
Tip #6: Decompose tasks to inch-pebble granularity. Inch-pebbles are
miniature milestones. Breaking large tasks into multiple small tasks
helps you estimate them more accurately, reveals work activities you
might not have thought of otherwise, and permits more accurate,
fine-grained status tracking.
Tip #7: Develop planning worksheets for common large tasks. If your
team frequently undertakes certain common tasks, such as implementing
a new object class, develop activity checklists and planning
worksheets for these tasks. Each checklist should include all of the
steps the large task might need. These checklists and worksheets will
help each team member identify and estimate the effort associated with
each instance of the large task he or she must tackle.
Tip #8: Plan to do rework after a quality control activity. Almost all
quality control activities, such as testing and technical reviews,
find defects or other improvement opportunities. Your project schedule
or work breakdown structure should include rework as a discrete task
after every quality control activity. If you don’t actually have to do
any rework, great; you’re ahead of schedule on that task. But don’t
count on it.
Tip #9: Plan time for process improvement. Your team members are
already swamped with their current project assignments, but if you
want the group to rise to a higher plane of software engineering
capability, you’ll have to invest some time in process improvement.
Set aside some time from your project schedule, because software
project activities should include making process changes that will
help your next project be even more successful. Don’t allocate 100% of
your team members’ available time to project tasks and then wonder why
they don’t make any progress on the improvement initiatives.
Tip #10: Manage project risks. If you don’t identify and control risks
, they will control you. Spend some time during project planning to
brainstorm possible risk factors, evaluate their potential threat, and
decide how you can mitigate or prevent them. For a concise tutorial on
software risk management, see my article "Know Your Enemy: Software
Risk Management" (Oct. 1998).
Estimating the Project
Tip #11: Estimate based on effort, not calendar time. People generally
provide estimates in units of calendar time, but I prefer to estimate
the amount of effort (in labor-hours) associated with a task, then
translate the effort into a calendar-time estimate. This translation
is based on estimates of how many effective hours I can spend on
project tasks per day, any interruptions or emergency bug fix requests
I might get, meetings, and all the other places into which time
disappears.
Tip #12: Don’t schedule people for more than 80%of their time.
Tracking the average weekly hours that your team members actually
spend working on their project assignments is a real eye-opener. The
task-switching overhead associated with the many activities we are all
asked to do reduces our effectiveness significantly. Don’t assume that
just because someone spends 10 hours per week on a particular
activity, he or she can do four of them at once; you’ll be lucky if he
or she can handle three.
Tip #13: Build training time into the schedule. Determine how much
time your team members typically spend on training activities
annually, and subtract that from the time available for them to be
assigned to project tasks. You probably already subtract out average
values for vacation time, sick time, and other assignments; treat
training time the same way.
Tip #14: Record estimates and how you derived them. When you prepare
estimates for your work, write down those estimates and document how
you arrived at each of them. Understanding the assumptions and
approaches used to create an estimate will make them easier to defend
and adjust when necessary, and it will help you improve your
estimation process.
Tip #15: Use estimation tools. Many commercial tools are available to
help you estimate entire projects. With their large databases of
actual project experience, these tools can give you a spectrum of
possible schedule and staff allocation options. They’ll also help you
stay out of the "impossible region," combinations of product size,
team size, and schedule where no known project has been successful. A
good tool to try is Estimate Pro from the Software Productivity Centre
(www.spc.ca).
Tip #16: Respect the learning curve. If you’re trying new processes,
tools, or technologies for the first time on this project, recognize
that you will pay a price in terms of a short-term productivity loss.
Don’t expect to get the fabulous benefits of new software engineering
approaches on the first try, so build extra time into the schedule to
account for the inevitable learning curve.
Tip #17: Plan contingency buffers. Things never go precisely as you
plan on a project, so your budget and schedule should include some
contingency buffers at the end of major phases to accommodate the
unforeseen. Unfortunately, your manager or customer may view these
buffers as padding, rather than the sensible acknowledgement of
reality that they are. Point to unpleasant surprises on previous
projects as a rationale for your foresight.
Tracking Your Progress
Tip #18: Record actuals and estimates. If you don’t record the actual
effort or time spent on each task and compare them to your estimates,
you’ll never improve your estimating approach. Your estimates will
forever remain guesses.
Tip #19: Count tasks as complete only when they’re 100% complete. One
benefit of using inch-pebbles for task planning is that you can
classify each small task as either done or not done, which is more
realistic than trying to estimate what percent of a large task is
complete at any time. Don’t let people "round up" their task
completion status; use explicit criteria to tell whether a step truly
is completed.
Tip #20: Track project status openly and honestly. Create a climate in
which team members feel safe reporting project status accurately.
Strive to run the project from a foundation of accurate, data-based
facts, rather than from the misleading optimism that sometimes arises
from fear of reporting bad news. Use project status information to
take corrective actions when necessary and to celebrate when you can.
These tips won’t guarantee success, but they will help you get a solid
handle on your project and ensure that you’re doing all you can to
make it succeed in a crazy world.
By Karl E. Wiegers
Lucy Doss
If you want to contribute an article (share your views,
experiences and thoughts) write in to us at info@123oye.com
send us your jobs / career related articles. We promise to give
you a chance to put your thoughts across to our visitors.
Jobnet Directory |
About Us |
Contact
|
|